Confidential Investor Information. This briefing is intended solely for authorized recipients engaged in a confidential investor discussion. If you are not an authorized recipient, you must immediately cease review, delete or destroy all copies, and notify invest@smartledger.technology. Unauthorized review, distribution, or use of this material is strictly prohibited.
Confidential Investor Summary

Florida’s inland platform for AI-scale compute infrastructure.

A two-site, 776.54-acre hyperscale data center platform in Frostproof, Polk County, designed for AI, cloud, colocation, high-performance compute, government, and defense demand — with renewable-first power planning, closed-loop cooling, and phase-gated institutional de-risking.

776.54 Acres Initial 250MW Phase 1GW Campus 1 Planning Case 3.5M+ SF Footprint

Transaction snapshot and project purpose.

Create a large-format, green, inland Florida hyperscale campus positioned for AI, cloud, colocation, and government-grade demand.

Land Platform
776.54

Total acres across two Frostproof sites: 472 acres on Hwy 27 and 304.54 acres on Old Fort Meade Road.

Campus Footprint
3.5M+

Programmed data hall / campus footprint with phased development, secure circulation, substation zones, and expansion flexibility.

Base Case
60 Mo.

Detailed feasibility base case is phased through Month 60, with long-range dual-campus master-plan upside shown separately.

Strategic Objective
3

Primary monetization paths: phased build JV, recapitalization into construction capital, or strategic sale after de-risking.

Investment thesis: scarce powered land with value-creation gates.

The first stage is designed to convert early risk reduction into institutional value before full vertical deployment.

01

AI & cloud demand

Hyperscale, AI training, inference, and cloud expansion are creating demand for large-load campuses capable of supporting 100MW–250MW+ blocks.

02

Scarce Florida platform

Florida is a major U.S. data center market, but large contiguous, lower-cost inland sites remain limited compared with coastal alternatives.

03

Risk-shaped phasing

Pre-construction capital targets land, utility, design, permitting, incentives, and anchor-tenant traction before major vertical capital is deployed.

04

Multiple exits

The project can be recapitalized, built through a JV, sold strategically, or scaled into long-term operating ownership after de-risking milestones.

First 12-month underwriting focus

  • Land control, environmental due diligence, geotech, and survey work.
  • Duke interconnection studies, transmission routing, and substation strategy.
  • Renewable energy, microgrid, and power-quality planning.
  • Architecture / campus basis-of-design package and market-facing concept package.
  • Permitting, municipal coordination, incentive applications, and anchor-tenant development.

Value inflection logic

1
Site controlSecure the land platform and close diligence risk.
2
Utility certaintyAdvance Duke studies, renewable strategy, and substation plan.
3
Permit progressReduce entitlement and environmental uncertainty.
4
Buyer-ready concept packageProduce BOD, renderings, floor plans, and capacity projections.
5
Anchor-tenant tractionSupport recapitalization, JV, or strategic sale.

Market and customer strategy.

Positioning is aimed at large-load users that value scale, resiliency, power certainty, and a faster path to expansion.

Demand drivers

  • AI / ML training and inference capacity needs.
  • Cloud platform expansion by hyperscalers.
  • Low-latency edge and content delivery demand.
  • Government and defense workloads requiring security and reliability.
  • High-performance compute and high-density infrastructure demand.

Competitive positioning

  • 60%–70% lower land cost than coastal alternatives, per sponsor materials.
  • Lower hurricane-risk profile than Miami / Tampa coastal sites.
  • Multiple utility options and fiber access along the US-27 corridor.
  • Scalable acreage with room for phased growth.
  • Renewable-first power and closed-loop cooling narrative for ESG and community acceptance.
Customer SegmentTypical DemandPriority NeedsTarget Users
Hyperscale Cloud100MW–200MW blocksReliability, pricing, long-tenor power certaintyAWS, Microsoft Azure, Google Cloud, Oracle Cloud, OpenAI
Enterprise Colocation10MW–50MW deploymentsPremium services, compliance, flexible termsFinancial services, healthcare, enterprise IT
Content & NetworkModerate capacityLow latency, interconnection valueNetflix, Akamai, Cloudflare, Fastly
Government & DefenseSecure long-term capacityFedRAMP / FISMA alignment, reliability, securityFederal agencies, DoD, state governments
High-Density ComputeFlexible large-load demandAI readiness, power density, rapid deploymentAI labs, HPC users, blockchain infrastructure

Two-site platform with frontage, scale, and phasing flexibility.

Illustrative renderings and tract documents support a two-phase campus concept in Frostproof, Polk County.

Campus 1: Hwy 27

472 acres

Primary hyperscale development site with planning case capacity up to 1GW. Current PSA cites $16.0M purchase price, 60-day due diligence period, 30-day close, and two 30-day extensions.

Up to 1GW planning casePrimary campusHwy 27 frontage

Campus 2: Old Fort Meade Road

304.54 acres

Expansion campus / secondary phased development with long-range planning case capacity up to 1GW. Current materials cite a purchase price for the 304.54-acre site; final figure should be confirmed against the latest PSA before investor distribution. 60-day due diligence period, 90-day close, and two 30-day extensions.

Up to 1GW long-range planning caseExpansion campusPurchase price pending PSA confirmation
Capacity is expected to be phased in approximately 250MW increments and remains subject to tenant demand, utility studies, power strategy, engineering, permitting, and financing.

Power, water, cooling, and network are the core underwriting variables.

The concept is framed around utility-scale redundancy, renewable energy, closed-loop cooling, and carrier-neutral connectivity.

Power Strategy

  • 138kV or 230kV preferred for dual-feed redundancy.
  • 200MW initial commissioning phase.
  • Ramp toward 1GW on Campus 1 and 400MW on Campus 2.
  • Customer-owned substation / microgrid option.
  • Duke-owned alternative also contemplated.
  • Renewable energy as primary source of power.

Water & Cooling

  • Municipal water allocation cited at 2M+ gallons.
  • Closed-loop cooling expected to reduce water use by approximately 90% versus traditional designs.
  • Projected full-build daily use: 200k–400k gallons versus 2M–4M traditional.
  • Reclaimed-water planning potential.
  • Water efficiency supports permitting and community-benefit narrative.

Network & Resiliency

  • US-27 corridor fiber access with multiple carrier-neutral options.
  • Feasibility targets under 5ms to Tampa.
  • Feasibility targets under 10ms to Miami / Orlando nodes.
  • Flat 24/7 load profile can support utility planning.
  • Secure vehicular circulation and campus perimeter strategy.
Duke engagement active Closed-loop cooling 90% water reduction target Carrier-neutral fiber Potential microgrid 2N backup power

Technical concept for institutional-grade operations.

Target standards are framed around Tier III / Tier IV reliability, high-density scale, and repeatable campus design.

Reliability

Tier III / IV target

Uptime target of 99.995%; Uptime Institute certification process contemplated in the feasibility study.

Efficiency

PUE target 1.15–1.25

Targeted performance versus 1.4–1.6 for traditional facilities, driven by optimized systems and cooling approach.

MEP / Design

AI-ready cooling

Gensler LOA and client-held engineers support prototypical MEP, structural, acoustic, and utility design.

Expansion

Repeatable campus logic

Shell and utility design supports phased 250MW increments, with expansion based on tenant demand, utility readiness, and financing milestones.

Gensler LOA Deliverables

  • Pre-design master planning and programming.
  • Phased campus plan across two sites.
  • Prototypical data center building concepts.
  • Conceptual site plans and zoning / capacity projections.
  • Basis-of-design narrative, floor plans, elevations, and campus renderings.
  • Market-facing conceptual package.

Steady-State Operating Frame

  • Uptime: 99.995%
  • Mean time to repair: under 2 hours
  • Water usage per kW: 90% below benchmark
  • Onsite 24/7 NOC and SOC
  • Critical spares inventory: $2M–$5M

Phased development roadmap.

A phase-gated development roadmap designed to advance land control, utility certainty, design, permitting, tenant traction, and construction readiness before major vertical capital deployment.

A
Phase A — Months 1–6Land acquisition/control, due diligence, Duke studies, design/BOD, permitting, environmental work, and tenant pursuit.
1
Phase 1 — Initial 250MW BlockConstruction-readiness, power shell planning, utility integration, tenant finalization, and first capacity deployment.
2
Phase 2 — Additional 250MW BlocksExpansion in additional 250MW increments based on tenant timing, technology requirements, power availability, and financing.
3
Long-Range BuildoutPotential path to 1GW+ campus scale over a longer phased timeline, subject to market demand, utility approvals, and end-user requirements.
S
Steady StateLong-term operations, refinancing, strategic sale, or continued expansion once operational milestones are confirmed and met.

Critical Path Items

  • Duke interconnection studies as longest-lead item.
  • FDEP air-quality permits for backup generation.
  • Long-lead electrical equipment procurement.
  • Closed-loop cooling engineering and procurement.
  • Municipal, county, and community support.

Proceed-to-Construction Criteria

  • Renewable and utility power path confirmed.
  • Anchor-tenant LOIs secured.
  • Phase 1 financing commitments secured.
  • Major permits in hand or final review.
  • Community support solidified.

Base-case financial profile.

The financial presentation has been reconciled to the stated Year-5 EBITDA margin target of approximately 48%.

Base Case vs. Upside Case. The base case uses the reconciled 48% EBITDA margin and current feasibility assumptions. Long-range master-plan upside, additional capacity, accelerated buildout, higher-margin operating cases, or strategic sale premiums should be presented separately and labeled as upside scenarios.
$1.824BYear-5 EBITDA at 48% margin on $3.8B revenue
$8.55B5-year cumulative revenue from the 1GW table
$4.10B5-year cumulative EBITDA using 48% margin
9–14%Unlevered IRR
15–22%Levered equity IRR
18–24xBase exit multiple range

1GW Campus Illustrative Revenue & EBITDA Planning Case

YearCapacity OnlineAnnual RevenueReconciled EBITDA
Year 1200MW$400M$192M
Year 2400MW$850M$408M
Year 3600MW$1.4B$672M
Year 4800MW$2.1B$1.008B
Year 51,000MW$3.8B$1.824B

400MW Campus Planning Case

YearRevenueStudy Notes
Year 1$24MUtilization ramp begins
Year 2$72MCapacity and lease-up expansion
Year 3$180MBlended pricing at $100/kW/month
Year 4$288MUtilization continues toward target
Year 5$408M85% utilization assumption
$195.8M Year-5 EBITDA $972M 5-year revenue $422M 5-year EBITDA 12–15% unlevered IRR 18–22% levered IRR 14–16x exit multiple

Phase-gated capital roadmap.

Capital is structured to separate Phase A de-risking from full construction deployment.

Phase A Investor

Land Acquisition + Pre-Development

$30M

Includes land control/acquisition, due diligence, site plan, initial architect fees, geotechnical studies, surveys, environmental studies, permits, PUD / zoning, Duke studies, and anchor-tenant market package.

Phase A is a land-control and de-risking investment. The immediate objective is not full vertical construction. Phase A capital is intended to secure the two-site land platform, complete diligence, advance Duke/power studies, produce the design/BOD package, progress permitting, and prepare the asset for recapitalization, strategic sale, construction JV, or anchor-tenant financing.

Return Options

  • Payback plus interest.
  • Equity participation.
  • Preferred equity with conversion rights.
  • Priority return at sale, recapitalization, or construction financing.
Shell Buildout Investor

Power Shell + AI-Ready Infrastructure

$5B + $1.5B

Campus 1 buildout target: approximately $5B. Campus 2 buildout target: approximately $1.5B. Broader master-plan framework references up to $9.7B across a dual-campus vision.

Return Options

  • Equity ownership.
  • Preferred return and repayment at sale.
  • Construction JV participation.
  • Strategic takeout by end user or infrastructure buyer.
Capital Stack ComponentIllustrative SharePurpose
Equity25%–30%Sponsor, strategic, and institutional capital for development and ownership.
Senior Debt50%–60%Construction and project finance debt after de-risking milestones.
Mezz / Preferred10%–15%Flexible capital layer for risk-adjusted returns and structured participation.
Government Grants5%–10%Non-dilutive support through infrastructure, energy, rural, and economic-development programs.

Incentives, tax advantages, and policy readiness.

The project is framed to combine Florida data-center tax advantages with broader community and infrastructure incentive pathways.

Florida / Project-Specific

  • Sales-tax exemption on electricity for qualifying data centers.
  • Sales and use tax exemption on infrastructure and equipment.
  • Potential property-tax abatements, phased assessments, or PILOT structures.
  • Study estimate for total tax benefits / incentives: $50M–$150M over project life.

Federal / Non-Dilutive

  • Opportunity Zone treatment for long-term capital.
  • New Markets Tax Credits via CDE structures.
  • EDA, DOE / IIJA, USDA Rural Development, and green-bank / infrastructure programs.
  • Broader materials cite $25M–$60M+ in grants and tax credits.

Policy / Permitting Posture

  • Early agency engagement with Frostproof, Polk County, CFDC, and Select Florida.
  • Water-efficient cooling and energy management positioned for disclosure readiness.
  • Community impact data prepared for potential future transparency requirements.

Sponsor platform and delivery ecosystem.

Current materials show a sponsor with federal / cybersecurity credentials, supported by design, construction, utility, and renewable energy relationships.

JustOne Frostproof

Sponsor / developer with federal contracting, Small Disadvantaged Business status, security / compliance positioning, government relations, incentives, and real-estate development experience.

Gensler

Architecture / campus planning LOA for pre-design master planning, phased campus study, prototypical buildings, renderings, and market-facing concept package.

Robins & Morton

Mission-critical construction LOA. References include 1,500+ employees, HostDime experience, SmartFab prefabrication, and Zurich / F&D surety support.

Duke / Energy Partners

Duke engineering analysis request filed. Sponsor energy-partner list includes renewable power and potential fuel-cell, battery, and microgrid solutions.

Risks and mitigation.

The feasibility study classifies overall risk as moderate, with key mitigation around phasing, water efficiency, and utility planning.

Risk CategoryWhy It MattersMitigation Posture
Power InfrastructureDuke capacity and timing can delay the project.Renewable-first strategy, early interconnection studies, multi-utility redundancy, substation / microgrid options, interruptible non-critical loads, and phased scaling.
Permitting & EnvironmentalAir permits, wetlands, wildlife, and zoning can stretch timelines.Pre-application strategy, phased permits, Phase I/II ESA, wetlands delineation, wildlife surveys, and municipal coordination.
Tenant AcquisitionSlow lease-up can impair financing and returns.Target 200MW hyperscale users first, widen to enterprise / government, and phase delivery to demand.
Construction Cost / ProcurementLong-lead equipment and market volatility can erode returns.10%–15% contingency, early-release procurement, mission-critical GC capabilities, and prefabrication strategies.
Water / Policy ScrutinyFlorida water use and disclosure rules can drive local resistance.Closed-loop cooling, 90% water-reduction target, municipal allocation, reclaimed-water planning, and proactive disclosure readiness.
Capital MarketsFinancing costs and investor appetite may change before construction.Phase-gated capital deployment, strategic sale optionality, recapitalization flexibility, and structured JV pathway.
Financial Model ReconciliationInconsistent EBITDA, capacity, or timeline assumptions can weaken investor confidence.Use a reconciled 48% EBITDA base case, separate upside scenarios, and confirm all capacity, land-cost, and schedule assumptions against final sponsor materials before investor distribution.

Data room support.

Diligence materials are available to qualified investors upon request and subject to NDA.

Investor Diligence Materials

Investor diligence materials may include PSAs, city support documentation, water-capacity support, renewable-energy partner materials, Duke/utility correspondence, Gensler LOA, engineering/construction partner documentation, site studies, tract materials, and sponsor feasibility assumptions.

PSAs & Site Controls Duke / Utility Correspondence Gensler LOA Feasibility Model Geotech & Environmental Studies Sponsor Credentials
Investor Opportunity

Multiple entry points. One platform-scale infrastructure thesis.

Best-fit investors include infrastructure funds, digital infrastructure investors, hyperscale strategic partners, mission-critical real-asset investors, utility / energy infrastructure partners, and capital partners comfortable with staged governance.

$30M Phase A Build / Sell / Recap Optionality Strategic JV Potential Anchor-Tenant Pathway

Request Investor Materials

Confidential and proprietary. Summary information for qualified investor discussions only.